Chemical Plant, Victoria, TX
BGM conducted a groundwater flow model and particle tracking analysis to evaluate the current groundwater recovery system. The objective of the existing groundwater recovery system was a landfill located at the western end of the plant property. The area is roughly 7 acres and contains certain plant wastes which were buried in the 1950s and 1960s.
Optimization simulations were run in order to determine the minimum pumping rate required to contain groundwater from the landfill while preventing surface water seepage into the remediation system from the barge canal. Specifically the model constraints were:
- the maximum pumping rate per individual well was 14 gpm, with maximum pumping rates of 25 gpm in selected wells
- each well was assumed to be able to sustain the maximum assumed pumping rate, and
- only the existing recovery wells could be utilized, no additional well locations were simulated.
BGM determined that an optimum solution could be achieved under the first and third constraint, but recommendations were made for the abandonment of selected wells and the installation of at least two additional pumping wells. Additional characterization of the geology in the vicinity of the barge canal was also required.
Areas of Expertise:
Cold-Eye / Peer Review
Contaminant Hydrogeology and Geochemistry
Groundwater Modelling
BGM’s Focus
Groundwater Remediation System Optimization
Groundwater Flow and Transport Modeling
Remedial System and Design
Location:
Victoria TX